Construction Progress

 


 

Clubhouse construction update


July 2022


 

We have had many changes to the Sherwin Rise Clubhouse and Wellness Hub construction over the last few months.

The services fit off stage has officially commenced in the Clubhouse along with installation of joinery, floor finishes, glazing to windows and wall tile install, bringing us that much closer to completion. 

The Wellness Hub is progressing superbly, with ceilings and walls finished, pool tiling commenced, and services being fitted off as well. 

On the external front, we are happy to announce that the landscaping works have started along with the bowling green surface installation in progress, BBQ area sheeting complete, and rendering nearing completion. 

We have also commenced the civil construction works for the roads leading to the clubhouse and stage 2 of our villas. 

Our site teams are kicking big goals this month with progress!