Construction Progress

 


 

Clubhouse construction update


April 2022


 

The Sherwin Rise Clubhouse is progressing well with successful construction milestones achieved in the last month. The wall framing and trusses is now complete with the roof installation expected to be completed in the next week on the main clubhouse roof then rolling onto the Wellness Centre roof.

Brickwork is nearing 50% complete along with window installation being installed closely behind with the aim to have the main Clubhouse at lock up
prior to the Easter break.

Rough-in services will commence in the next week internally in preparation for plastering works to commence in late May.

The Bowling green subgrade has been prepared and ready for the specialist contractor to commence preparation to construct the bowling green surface.