Construction Progress
Construction Update
April 2022
The site of Ardency Kennedy Place is changing day by day as our construction progresses.
The east wing of the building now has the Level 3 slab poured and the formwork is currently underway for the Level 4 slab.
On the west wing of the building, the Level 2 slab has been poured as the formwork for the Level 3 slab is underway. Metal screening has also been installed around the
building – this is a safety measure in place to protect both workers on site and also those below from falling materials.
The glass façade installation has commenced on the ground level and will continue to be installed progressively over the next few months.